Set maximum test time via maestro config?

Hi, 

 

Is there a config option for a maestro to set a maximum time for a test to run?

 

In other words can we restrict the maximum time a composition can run for via a maestro server config? I took a look at the config for a maestro and did not see an option when scanning through.

 

We found some users were running tests everyday for 12+ hours, this is filling up the disk space of the RSDB fast. Most users in our company do not have access to the server configs, so this may be the best option for restricting them.

 

Thanks

 

Alex

SOASTA Employee
Posts: 1,499
Registered: ‎04-30-2012

Re: Set maximum test time via maestro config?

Hi Alex,

 

There is a Maximum Duration setting in the composition distribution setup where you specify the ramp, number of users, parallel repeats, etc...

 

Cory
Director of Performance Engineering - East
Have You Seen The Tutorial Videos? Click Here
Premier
Posts: 78
Registered: ‎11-08-2013

Re: Set maximum test time via maestro config?

Hi Corey,


I am aware of that, I need something that will override that setting on a level where a normal user does not have permission to change.

 

I noticed it's possible to add your own custom config (via the GUI) to maestros, is it possible to add a setting there to do what I need it to?

 

Thanks


Alex

SOASTA Employee
Posts: 1,499
Registered: ‎04-30-2012

Re: Set maximum test time via maestro config?

Hi Alex,

 

I checked with Engineering and this is not possible currently.

 